Eaton Canyon foothills above Altadena, CA, with the Mt. Wilson Toll Road winding up the San Gabriel Mountains

How to Rebuild Your Home in Altadena: Step-by-Step Guide (2026)

Key takeaway

To rebuild a home in Altadena after the January 2025 Eaton Fire, follow LA County's six steps: debris removal, prepare plans, apply for a Disaster Recovery Permit, complete plan review, build with inspections, and get a Certificate of Occupancy. Homes inside Pasadena city limits use the City's process. Like-for-like rebuilds are usually fastest.

Rebuilding after the Eaton Fire follows a clear order. This guide walks you through it, with a link to the official source for each step.

Quick answers

  • •LA County's official path has 6 steps: debris removal → prepare plans → start your permit application → permit process → build and inspect → move in.[1]
  • •Know who issues your permit first. LA County handles unincorporated Altadena. The City of Pasadena handles homes inside City limits.[2][3]
  • •Like-for-like is usually fastest. You can rebuild the same home, up to 10% or 200 sq ft larger (whichever is greater).[4]
  • •Most County permit fees are not collected from eligible owner-occupants. Pasadena waives fees for eligible red-tagged homes.[5][6]
  • •Your contractor must use a fixed-price contract. The down payment can't be more than $1,000 or 10%, whichever is less.[7]

Want this turned into a plan for your lot? We'll visit your property and give you a free, written Rebuild Roadmap.

(From the Altadena Rebuild Team, our sponsor)

Free download: The Altadena Rebuild Checklist. Every step on this page as a printable checklist.

What are the steps to rebuild in Altadena?

StageWhat happensTypical owner tasks
0. Get readyRecords, insurance, money, jurisdictionGather documents; check deadlines
1. Debris removalPhase 1 (hazardous waste) and Phase 2 (debris)Confirm your lot is cleared
2. Prepare plansChoose like-for-like, pre-approved, or customHire a designer, or pick a pre-approved plan
3. ApplyDisaster Recovery Permit (County) or City permitSubmit plans and forms
4. Permit processReviews by Planning, Building, Fire, HealthAnswer comments; ask for fee deferral/waiver
5. Build and inspectConstruction and inspectionsSign a fixed-price contract; track payments
6. Move inCertificate of OccupancyFinal walkthrough; update insurance and tax records

Source: LA County Road to Rebuilding.[1]

Step 0: What should I do before I start?

Confirm your jurisdiction

A Pasadena mailing address doesn't always mean the City issues your permit. Check your address with the County's “City or Unincorporated” lookup.[8]

Check your deadlines

  • •CalAssist Mortgage Fund: apply by Nov 2, 2026.[9]
  • •SCE Wildfire Recovery Compensation Program: claims due Nov 30, 2026.[10]
  • •Property tax relief (Assessor form ADS-820): 24 months for the Eaton Fire, about Jan 7, 2027.[11]

Know your insurance numbers

Write down your dwelling limit, other-structures limit, extended replacement cost, code-upgrade coverage, and ALE limit.

California lets you combine dwelling and other-structures limits if the dwelling limit falls short, and gives you at least 36 months from the first actual-cash-value payment to collect full replacement cost.[12] More on our Insurance page

Plan where you'll live

The County can permit a temporary housing unit (a manufactured home, mobilehome, or RV) on your lot if your legal home was destroyed or made unlivable. It can't be placed on the debris field.[13]

Step 1: Is my lot cleared of debris?

  • •Phase 1: hazardous materials removed by the EPA.[4]
  • •Phase 2: debris removed by the U.S. Army Corps of Engineers, or by your own contractor if you opted out.[4]
  • •You can apply for permits at any time. In the County, your permit is issued only after both phases are done.[4]

Step 2: How do I prepare plans?

Choose a path:

PathSpeedSizeDesign cost
Like-for-likeUsually fastestSame, or up to +10% / +200 sq ftLower
Pre-approved planShorter, more predictable reviewSet by the plan; must fit your lotLower (design already done)
Custom / biggerLongestUp to current zoning limitsHigher

Sources: [4][14]. For the full comparison, see our post “Like-for-like vs. a bigger rebuild”.

Self-certification can shorten review. A qualified architect or engineer certifies the plans meet code, so the County skips the full building plan check. It isn't available on hillside, liquefaction, or landslide-risk lots.[15]

Rules that may lower your cost:

  • •No rooftop solar or battery required for rebuilt homes, but the home must be solar-ready.[16]
  • •Rebuilds may follow the 2022 building code instead of the 2025 code, except for fire-safety rules.[16]

Not sure which path fits your lot? Our partner architect and our build team can compare like-for-like, pre-approved, and custom on one page for you. [Owner to confirm]

Step 3: How do I apply for a rebuild permit?

  • •County: apply online through EPIC-LA (bit.ly/RebuildEPIC) or in person at the Altadena One-Stop Permit Center, 464 W. Woodbury Rd., Suite 210. Walk-in hours are Mon–Fri 8:00–4:30.[17][18]
  • •Pasadena: red-tagged homes have an assigned planner. Book a 30-minute virtual consultation with the Planner of the Day.[3]
  • •Free help: One-Stop rebuild consultations run Mon/Wed/Fri 8:30–12:30, (626) 424-6743.[18]

Step 4: What happens during plan review?

  • •In the County, Planning, Building & Safety, Fire, and Public Health all review your plans.[4]
  • •Ask for the fee deferral (County) or fee waiver/refund (Pasadena).[5][6]
  • •Free AI zoning PreCheck for R-1 Altadena lots; results take up to 10 business days.[19]
  • •Half of the County's single-family Eaton permits issued so far took 147 days or less from application to permit. [Estimate: our analysis of public EPIC-LA data, Oct 22, 2026][20]

Full details: Permits page

Want us to handle plan check for you? We coordinate the drawings, the reviewer comments, and the construction pricing in one place. [Owner to confirm scope]

Step 5: How do I hire a builder and pass inspections?

Hire carefully

  • •Check the license at cslb.ca.gov. For a whole-home rebuild, look for a B – General Building license.[7]
  • •Rebuild contracts must be fixed price. Time-and-materials and cost-plus contracts aren't allowed.[7]
  • •The down payment can't be more than $1,000 or 10%, whichever is less. Later payments must match work done or materials delivered.[7]
  • •If the contract is signed at your home (not at the contractor's office), you have 7 business days to cancel a contract to repair or restore a home damaged in a declared disaster.[21]
  • •In a declared disaster area, contracting without a license can be charged as a felony.[22]

Inspections

County inspectors check the work at set stages. Don't cover up work before it's inspected.

Step 6: When can I move back in?

Once final inspections pass, you get a Certificate of Occupancy.[1][4] Then:

  • •Tell your insurer the home is complete, and ask about recoverable depreciation.
  • •Ask the Assessor about keeping your old tax base. For the Eaton Fire you have 8 years to rebuild a comparable home and keep it.[11]

FAQ

Sources (all checked Oct 22, 2026)

  1. 1.

    LA County, Road to Rebuilding

  2. 2.
  3. 3.
  4. 4.
  5. 5.
  6. 6.

    City of Pasadena, Fire Rebuild Fee Waiver and Refund Program

  7. 7.

    CSLB, Disaster Help Center

  8. 8.
  9. 9.
  10. 10.
  11. 11.

    State Board of Equalization, LTA 2026/022 (Publication 802)

  12. 12.
  13. 13.

    LA County Recovers, Temporary Housing Permit Process

  14. 14.
  15. 15.
  16. 16.
  17. 17.
  18. 18.
  19. 19.

    LA County Recovers, LA County eCheck / PreCheck

  20. 20.

    LA County EPIC-LA Eaton/Palisades cases (public ArcGIS layer)

    [Estimate: our analysis; method in /blog/how-long-altadena-rebuild-permits-take/]
  21. 21.

    California Civil Code §1689.6(c)

    (read via leginfo search snapshot; direct load blocked from our checker)
  22. 22.

    California Bus. & Prof. Code §7028.16

    (read via leginfo search snapshot)

Last reviewed: October 22, 2026

Altadena Rebuild Guide

Free Rebuild Toolkit

Official help, a step-by-step checklist and key deadlines in one free download.

Important information

An independent guide. Altadena Rebuild Guide is a free, privately run resource sponsored by R&M Builders Inc, a licensed California general contractor. It is not a government website and is not affiliated with or endorsed by Los Angeles County, the City of Pasadena, the State of California, FEMA, or any other agency or nonprofit.

Based on official sources. Our guides summarize information published by government agencies and other official sources, linked on each page. Programs, rules, fees, and deadlines can change without notice, so please confirm the details with the official source before you make decisions.

General information only. Nothing on this site is legal, tax, financial, insurance, or engineering advice. For advice about your property, talk with a qualified professional.

Estimates, not quotes. Any costs, timelines, or examples are general planning estimates. They are not quotes, offers, or guarantees, and your project may differ.

Outside websites. Links to other sites are provided for convenience. We don't control their content and aren't responsible for it.

Your choice of builder. You're free to hire any licensed contractor. Requesting a consultation doesn't obligate you to anything, and we don't pay or receive referral fees.

Your information. When you submit a form, we use your details to respond to your request. Texts are sent only if you opt in. See our Privacy Policy.